Update on Sabine Pass and Corpus Christi

Corpus Christi: Train 3 Completion in H2 2021 | Sabine Pass: Train 6 Completion in H1 2023
Cheniere Energy said on Friday (Nov. 01) that it expects to reach substantial completion of the third liquefaction train at its Corpus Christi LNG export plant in Texas earlier than previously expected in the H1 2021. Earlier, the company said it expected to complete the train in the H2 2021. Cheniere also said in its Q3 2019 earnings release that it expects to complete the sixth train at its Sabine Pass LNG export plant in Louisiana in H1 2023… Cheniere has said it hopes to make a decision to build Corpus Stage 3 in 2020, which would enable the plant to enter service in 2023.

Link to Cheniere Presentation

Categories: Cheniere Energy, Corpus Christi, Sabine Pass


Copyright © 2020, LNG Allies